Completed the construction of the new Harrison Blvd. Substation acting as the prime contractor
Installation of a 115kV circuit switcher, 115/13.8 kV 24/32/40 MVA LTC transformer, 13.8kV metal-clad switchgear, 13.8kV 7.2 MVAR, 2 stage capacitor bank, and getaway ducts and manhole system for four new 13.8kV feeders.
Detailed coordination between the substation work and transmission and distribution line work.